Examples and samples of estimates. How is the estimate for finishing work correctly drawn up? Estimated calculation for finishing work

(We consider examples on the basis of TEP-territorial unit rates, similarly and FER-federal unit rates,
according to the Reference Estimate and Normative Base (new edition))

Let's look at example # 5 of budgeting, this example will be more complicated:

For example, let's say that the customer asks to repair the walls in the apartment.

We take a tape measure, a piece of paper, a pen or pencil and go out to inspect the place of repair, i.e. we go to the object.
Arriving at the site, we find out that the walls need to be repaired only in one room.
Here at the place of the Customer's representative, we specify what exactly the Customer wants.
The customer wants (we are considering only walls without slopes):

1. Clean the walls from water-based paint;
2. Level the plaster of the walls;
3. Apply a putty;
4. Paint the walls with water-based paint.

Ask the Customer for all the details, this will help you when choosing prices in the future.
After asking the Customer, we agreed that:

  1. We will first clean off the old paint from the walls;
  2. Priming the walls before leveling the plaster with a primer, to adhere the new layer of plaster to the old one (in other words, so that our plaster does not fall off);
  3. To level the plaster of the walls with the "Rotband" plaster mixture, the thickness of the plaster layer is up to 10 mm.
  4. Then prime the walls again with a primer, before applying the putty and water-based paint so that all this does not crack, fall off and adhere tightly to the wall.
  5. Apply a putty to the walls to smooth out wall defects after plastering;
  6. And the last thing, to paint the walls with water-based paint, the painting was discussed with the Customer, it will be improved.
Stage II:

We have clarified the task, now we need to decide on the volumes. It is good if the Customer gives you a copy of the floor plan, which shows the dimensions of the renovated premises. And if not, then we will give a tape measure and measure the width and length of the room, as well as the width and height of the door and window openings tape measure yourself.
Suppose that when measuring the width of the room we got 4.0 m, the length of the room is 6.0 m, the height of the room is 2.85 m.The height of the doorway is 2.0 m, the width is 1.0 m, the height of the window opening is 1.5 m. , and the width is 1.4 m.
Be sure to measure the dimensions of door and window openings in the room. When calculating the volumes of the walls, we will subtract the areas of the door and window openings from the total total area of ​​the walls of the room, since the amount of work to level the plaster of the walls is determined by the area of ​​only the surface that will be aligned. (HPESNr 81-04-OP-2001 State element estimate norms for repair and construction works... General Provisions. Calculation of the scope of work (edition 2009), clause 2.42. Plastering area interior walls should be determined minus the areas of openings along the outer contour of the boxes and the area occupied by the stretched platbands, and the height of the walls should be taken from the clean floor to the ceiling.)

But, the area of ​​painting the walls with water-based paint is determined without deducting the areas of openings and without taking into account the areas of window and door slopes only if we paint the slopes too. (HPESNr 81-04-OP-2001 State elementary estimate norms for repair and construction work. General provisions. Calculation of the volume of work (edition 2009), clause 2.51. areas of window and door slopes, side surfaces of niches, but taking into account the areas of pillars and lateral sides of pilasters.)

But since we do not paint the slopes, but only the walls, therefore, the area of ​​painting the walls with water-based paint is taken specifically according to the area of ​​the painted surface.

Having photographed the walls mentally and measured them, we return to our place of work and proceed to the second stage.

We consider the area of ​​the walls: (6.0 + 4.0) * 2 * 2.85-2.0 * 1.0-1.5 * 1.4 = 52.9 m2.
Now we write to the defective statement what we need to do:

  1. Remove paints from wall surfaces by hand. We write to the defect list - Manual cleaning of the wall surface from 52.9 m2 paints.
  2. Prime the walls before leveling the plaster with a primer. We write in the defect list - Priming the surface of the walls with a primer before leveling the plaster 52.9 m2.
  3. Align the plaster of the walls with the "Rotband" plaster mixture, with a plaster layer thickness of up to 10 mm. We write in the defect list - Leveling of plaster walls with dry mortar "Rotband" thickness up to 10 mm 52.9 m2.
  4. Prime the walls after leveling the plaster, before applying putty and water-based paint. We write in the defective statement - Priming the surface of the walls with a primer before applying putty and water-based paint 52.9 m2.
  5. Put putty on the walls to smooth out any defects after plastering. We write to the defect list - Putting putty on the walls to level out defects after plaster 52.9 m2.
  6. Paint the walls with water-based paint. We write in the defect list - Improved painting with water-based compositions on the plaster of the walls.
Notice one important detail, all the details are written in the defective statement.

Specifically in our case, we wrote not just "Leveling of plaster walls with a dry mortar mixture" Rotband ""; "Painting with water-based compositions of walls improved", and "Leveling of plaster walls with dry mortar mixture" Rotband "thickness up to 10 mm";" Painting with water-based compositions on plaster improved walls "as requested by the customer.
Why such details, you will understand later when looking for prices.
Well, in our case, the defective statement is ready, see below:


"APPROVED"

________________ /______________________ /

"______" ____________________ 20___

Object: Apartment

DEFECTIVE STATEMENT

to repair the walls in the room

No. pp Name of works and costs unit of measurement Quantity
1 2 3 4
1. Manual cleaning of wall surfaces from paints m2 52,9
2. Priming the surface of the walls with a primer before leveling the plaster m2 52,9
3. Leveling the plaster walls with a dry mortar mixture
"Rotband" up to 10 mm thick
m2 52,9
4. Priming the surface of the walls with a primer
before applying putty and water-based paint
m2 52,9
5. Applying putty to walls to smooth out defects after plastering m2 52,9
6. Painting with water-based compositions on wall plaster, improved m2 52,9

Compiled by: _______________________________________________________
(position, signature, full name)

Checked by: _______________________________________________________
(position, signature, full name)


After the defective statement is ready, it is given to the Customer for approval.
And after the Customer approves the defective statement, we start drawing up the estimate.

Budgeting.
To draw up an estimate, we need TEPr - Territorial unit prices for repair and construction work; TEP-Territorial unit prices for construction work.
If you are already familiar with the estimated program, then all these TEPr, TEP are in it.
So, we have a cleanup of old paint, leveling the plaster, then painting with new paint, i.e. repair, therefore we are looking for prices first in the repair sections - TEPr - Territorial unit prices for repair and construction work. And if there are no prices suitable for us in the repair sections, then we are looking for them in the construction parts.
But when repairing, initially, prices are always looked for in the repair sections.
Initially, we manually clean the surface of the walls from paints. There is no direct quotation for this type of work, so we will look for a quotation applicable. Since the first type of work is related to paints, i.e. cleaning from paints, then we are initially looking for TEPR-painting work. This will be TERr Section 62 Painting.
Further in TEPr section 62. Painting, we are looking for cleaning from paints. This will be the applicable rate TEPr 62-41-1.
For the first item in the defective statement, we found a quote - TEPr 62-41-1. We insert it into our estimate.

Now we are looking for a quote for the second item on the defective statement.
The second type of work - priming the surface of the walls with a primer before leveling the plaster, we will not look for now, since usually the priming is included in the prices for leveling the plaster.

We are looking for the third type of work at once - leveling the plaster walls with a dry mortar mixture "Rotband" up to 10 mm thick.

Since the third type of work is related to plastering, i.e. leveling plaster, then we are looking for TEPR-plastering work. This will be TEPr Section 61 Plastering.
Further in TEPr section 61. Plastering works, we are looking for leveling the plaster walls with a dry mortar mixture up to 10 mm thick. This will be the TEPr 61-1-9 rate.
We look that the price of TEPr 61-1-9 is open, this means that the cost of the main material (in our case, it is a plaster mix "Rotband") must be taken in addition to this price according to TSSTs, since in the price TERr 61-1-9 it (the main material) is not taken into account. Therefore, to the price TEPr 61-1-9 we additionally take the plaster mix "Rotband". The cost of materials is searched for according to the collection of TSSTs. TSSTS - a territorial collection of estimated prices for materials, products and structures used in construction. It consists of five parts:

  1. TSSTS 2001 Part I. Materials for general construction works
  2. TSSTS 2001 Part II. Building construction and products
  3. TSSTS 2001 Part III. Materials and products for sanitary works
  4. TSSTS 2001 Part IV. Concrete, reinforced concrete and ceramic products. Nonmetallic materials. Commercial concrete and mortars
  5. TSSTS 2001 Part V. Materials, products and structures for installation and special construction works
Since the leveling of plaster in our company refers to work with mortars, we are looking for a quote for the cost of the "Rotband" plaster mix according to TSSTS 2001 Part IV. Concrete, reinforced concrete and ceramic products. Nonmetallic materials. Commercial concrete and mortars. This will be the price TSSTS 402-0077. In addition, we take the coefficient for the consumption of the material, the consumption of the Rotband plaster mixture according to TSSTs 402-0077 will be 9.6 kg per 1 m2 with a layer thickness of 10 mm: 52.9 * 9.6 = 507.84 m2

For the second and third points in the defective statement, we found the price - TEPr 61-1-9. We insert it into our estimate.

Next, we turn to the fourth and fifth types of work - priming the surface of the walls with a primer before applying putty and water-based paint and applying putty on the walls to level out defects after plastering. We, too, will not look for these types of work for the time being, just like the second one. Let's first consider the sixth type of work - Painting with water-based compositions on the improved plaster of walls, and then we will explain why we missed the fourth and fifth types of work.

Since in TEPr there are no prices for painting with water-based compositions for improved plastering of walls, we turn to the building parts TEP - Territorial unit prices for construction work.
Looking for in TEP - Finishing work... This will be TEP part 15. Finishing work. The suitable price for us is TEP 15-04-005-03.
Consider this rate TEP 15-04-005-03 in more detail, an interesting rate.

First of all, we need to find out if the primer and putty are in the TEP 15-04-005-03 price.
We look at GESN 81-02-Pr-2001 State element estimate norms for construction work. Appendices (2009 edition), Appendix 15.11 - Scope of work when painting with polyvinyl acetate aqueous emulsion compositions - improved on plaster. Here, in the table, we see that the priming and filler are already included in the price for painting with water-based compositions on the improved plaster of walls. And therefore, we will not take separate prices for priming and filler before painting the walls with water-based paint.

At the price TER 15-04-005-03 you may have a question: "How is the primer included in the price if the price does not include the cost of this very primer at TSSTs?"

We explain that the consumption of paint as part of the price TER 15-04-005-03 for improved painting is so great that part of this consumption can replace both the consumption of the primer and the cost of the primer itself. Therefore, it makes no sense to adjust this price for a primer (see the Letter of the Ministry of Regional Development of the Russian Federation of July 21, 2009 No. 22729-IP / 08).

Now we can say that for the fourth, fifth and sixth items of the defective statement, we have found a suitable price - TER 15-04-005-03.

The estimate is almost ready, it remains to add all the necessary coefficients from the appropriate MDS - Methodological documents in construction, such, for example, as in clause 4.7. MDS 81-35.2004, if there are complicating factors and conditions for the production of these works, and reducing coefficients to overhead costs and estimated profit during repairs, this is also from MDS ( read more often and study the MDS before making estimates), and you can release it.
The estimate will look like this, look

Just do not forget that the estimated prices in the collections and programs are based on 2000 prices. Therefore, you need to multiply the final estimated cost in this estimate by the corresponding index of translation into current prices.
The index of translation into current prices is different for each region.

After all that has been done, the finished estimate can be given to the Contractor for approval, and then for the Customer's approval.

AND NOW TRY TO SOLVE THE PROBLEMS OF MAKING AN ESTIMATE AND CHECK YOURSELF IN THE SECTION:

This page presents some examples of estimates for construction and renovation work .
This examples of construction estimates for already completed (once, by someone) work or abstract estimates on a typical roof repair, premises renovation, office renovation etc.

All the estimates presented here have one thing in common: they are all compiled in the 2007 Estimate program.

The estimates given here will clearly show you how it looks estimate created in the estimate 2007 program.
The submitted files may contain the same others that ours can create: KS-2, KS-3, Invoice, Contract agreement, etc.

For convenience, the list of estimates is divided into groups and each estimate is supplied with brief description.
Click on the name to download the estimate.

Select a group: All groups Improvement Roof repair Premises repair

In the estimate, the cost of work and materials for the repair of a roof section made of metal tiles of a public building (not private house). According to the estimate, the following works are carried out: complete replacement of metal roofing on the roof section with preliminary repair of the lathing and processing wooden elements fire-retardant composition. The area of ​​the roof section to be repaired is 730 m2.

Overhaul estimate soft roof technical floor. Roof area 1,300 m2. In the estimate, the calculation of the following works was made: dismantling of the old roofing carpet with garbage disposal, dismantling of inoperative ventilation pipes, installing a new screed made of sand concrete, priming and installing a new two-layer roofing carpet from Uniflex on fiberglass.

Very revealing estimate for office renovation- 500 lines, 11 sections: general construction and finishing works, ventilation and air conditioning, water supply and sewerage, structured cabling systems, access control system and other works.

Finishing is the final stage of repair, during which a certain list of works is performed. The result of their implementation is ready-to-use residential, administrative and industrial premises. To estimate the estimated costs, an estimate is made. It determines the volume and content of technological operations for the transformation of premises, the complexity of their implementation, the range and quantity necessary materials... How to make an estimate for finishing work? To do this, you need to know the algorithm for its registration and competently use the regulatory documents that govern the calculations.

Simple circuit

The easiest way to draw up an estimate for finishing work is in demand when performing repairs on your own or with the involvement of a hired team. In this case, the cost of materials is determined in accordance with the selected price segment and the average cost in the construction market and in shopping centers. The cost of finishing work is not taken into account or depends on the terms of the contract with the contractors. The calculation of the amount of necessary financial investments to complete the repair is carried out in several stages and includes the following steps:

  • inspection of the premises and assessment of its condition;
  • measuring the area of ​​the floor, walls and ceiling;
  • choosing a design concept for a room, taking into account its purpose and the tastes of real estate owners;
  • determination of the list of works required to create the designed interior, and their cost;
  • counting the amount of materials required for finishing, and determining their cost depending on prices.

When you independently transform the interior of the room, you should also include the funds spent on the purchase of tools and special devices for performing different types repair work. In addition, it is necessary to provide for the allocation of a certain amount for cleaning the premises at the end of the finishing of the premises. Removing bulky construction waste on your own can result in a significant fine.

Determination of costs in accordance with the standards

How to make an estimate using the algorithm established regulatory documents? Usually, its design is delegated to special organizations or the design department of a construction company, which will carry out finishing and repair work. However, you can make an estimate with your own hands, having studied special literature or using as a sample a similar document developed to restore a room similar in overall dimensions, technical condition and purpose.

At the initial stage, you should assess the financial capabilities of the owner of the room, taking into account the prices of materials on the construction market. Then the state of the room is determined and a list of necessary technological operations is drawn up. The preparatory work is completed by measuring the dimensions of the room with an indication of the available structural elements. Based on the data received, fill out the form of the defective statement. It reflects the slightest changes in the interior of the room and describes all the details of the transformation of the interior with the obligatory indication of the size of the changed areas.

After registration, the defective statement is agreed with the owner of the premises and, along with the contract, serves as the basis for drawing up an estimate. It is transferred to the estimate department or directly to the specialist performing the calculations.

Types of estimates and methods of calculation

On the territory of the Russian Federation, estimates can be drawn up in several ways, including:

  • basic index;
  • basic compensation;
  • resource-index;
  • resource.

In the first case, to determine the cost of services and materials, a system of forecast indices is used in relation to the base prices for works and raw materials according to the data of the previous period. The final prices are calculated on the basis of basic indicators.

When choosing a basic compensation method, the projected cost of the necessary materials and services is determined taking into account the projected tariffs. Its refinement takes place directly on construction site... If the calculations are carried out according to the resource method, then within their framework, resource tariffs and forecast prices are calculated. In this case, the estimate for finishing work is drawn up taking into account the consumption rates of materials, which are regulated by the regulatory documentation. When using the resource-index method, the calculation according to the system of price indices is combined with the resource method.

The choice of a specific option is not regulated by law, therefore, the methodology for making estimates is determined according to the characteristics of the object. The most popular algorithms include resource-index and resource methods.

Formation of estimates

How is the estimate made? It is formed by summing up several types of costs, which are:

  • straight;
  • waybills;
  • planned.

Direct costs represent funds for payment of materials, labor of executors carrying out finishing work and operating costs. Their calculation is based on:

  • a list of technological operations to transform the interior;
  • volume of work performed;
  • accepted norms.

Overhead costs include the cost of organizing the process of carrying out repairs, management and maintenance. Usually, their value is a certain percentage of direct costs and is calculated in accordance with established norms or according to the accounting system at the enterprise. The calculation of the estimate with the inclusion of overhead costs can be performed both for an aggregated indicator and for a separate type of work.

Planned savings include funds that cover expenses that are not directly related to construction. Among them are the costs of paying taxes, creating favorable conditions for the work of employees and stimulating their activities. Planned costs are formed on the basis of industry-wide or individual standards.

Nuances of calculations

How to make a correct estimate for finishing work in the absence of the necessary experience? You can use a suitable project as an example, making the appropriate amendments. The final figures are adjusted taking into account the number of employed specialists, their qualifications and other parameters. To simplify the preparation of estimates, special programs are also used, similar in functions to "1 C Accounting" and containing samples of all variants of estimate documentation.

The calculation of the estimated cost of converting the interior is carried out using standard estimates, special projects, established standards of the current price lists. They are tied to a specific type of work and provide the ability to vary prices, despite the outdated regulatory framework.

In particular, at the stage of preparation, if necessary, priming and filling the surfaces of walls and ceilings, the price is calculated by summing the cost of materials and the cost of performing work. Before completing the formation of the estimate, all costs are combined. Typically, the actual cost exceeds the design value by about 10-15%.

Possible shortcomings and pitfalls

If the preparation of the estimate was entrusted to a specialized organization or department of the enterprise that will carry out the repair work, then the owners of the premises can check the correctness of its calculations. The easiest way to overestimate the cost of work is to incorrectly measure the dimensions of the room and assess its condition. The increase in the number of finishing materials and complex preparatory operations significantly increase the level of repair costs.

Time-consuming preparatory work, which is easy to do without, also contributes to the increase in costs. On the other hand, saving on primer and putty can lead to the fact that over time the facing material will lose its original appearance and require replacement. In addition, inadequate surface preparation will not provide adequate adhesion and will lead to delamination of the finish.

Other ways to increase the cost of the estimate include:

  • overpricing of materials;
  • inclusion of works not provided for by the project;
  • purchase of expensive materials without taking into account their quality and expediency of use;
  • failure to provide pre-agreed discounts on payment for materials and services rendered;
  • adding to the general item of expenses the cost of delivery of components, materials and tools.

Another marketing move is a significant understatement of the cost estimate at the stage preparatory work and signing the contract. This method is aimed at attracting customers, for whom, as a result, after the start of the repair, it turns out to be unforeseen expenses in a significant amount. For bona fide contractors, the cost of the estimate does not change significantly throughout the entire provision of finishing services.

A sample of a ready-made estimate for repair and finishing work in an apartment with a total area of ​​64 m2, a new building at the address: Residential Complex "Finsky-Potapovo 3A" microdistrict.

Estimate number 4 for the implementation of repair and finishing work

Estimate for the purchase of rough materials

Name of works Unit rev. Qty

Pricing

in rubles

Price

in rubles

Dismantling work
1 Ceiling joints (rustic) r.m 8 150 1200
2 Dismantling of sockets, switches, lamps PC. 12 75 900
3 Dismantling the complete electrical panel PC. 1 650 650
Total: 2 750
Construction works
1 Laying of partitions made of tongue-and-groove blocks or foam concrete up to 100 mm thick sq.m 5,8 420 2436
2 Metal jumper device r.m 2 280 560
3 Bath screen device from blocks PC. 1 1100 1100
4 Steam insulation device ("penofol", "penoplex") balcony - floor, ceiling, walls sq.m 27 360 9720
5 The device of coating thermal insulation "Akterm" sq.m 0 180 0
6 Waterproofing joints adjacent to the street sq.m 6 185 1110
Total: 14 926
Painting and plastering works
1 Plastering of walls (along beacons) up to 20 mm sq.m 25 385 9625
2 Alignment of walls (as a rule) up to 10 mm - rooms, kitchen, corridor, pantry sq.m 154,5 200 30900
3 Alignment of ceilings (as a rule) up to 10 mm kitchen, corridor, pantry, balcony sq.m 28 250 7000
4 Sealing of ceiling joints (rustic) r.m 8 150 1200
5 Surface primer (2 layers) ceiling, walls sq.m 0 60 0
6 Surface finishing - ceiling, walls sq.m 0 45 0
7 Putty ceilings for painting (complex of works) kitchen, corridor, pantry, balcony sq.m 28 350 9800
8 Painting ceilings with w / e paint in 2 times sq.m 28 180 5040
9 Putty of walls for painting (complex of works) sq.m 154,5 280 44805
10 Painting walls with w / e paint in 2 times sq.m 154,5 140 21630
11 Plastering window slopes up to 300 mm r.m 15 260 3900
12 Filling of slopes for painting (complex of works) r.m 15 280 4200
13 Coloring of slopes with w / e paint in 2 times r.m 15 180 2700
14 Installation of arched painting corners with sealing of seams and joints r.m 22 65 1430
15 Painting of pipes with a diameter of up to 50 mm r.m 26 120 3120
Total: 145 350
Joinery and carpentry works
1 Installing the door block (ready-made kit) PC. 5 3000 15000
2 Installation of slatted ceilings (up to 10 sq.m.) sq.m 4,4 880 3872
3 Installation plastic window sills up to 300 mm r.m 4,5 750 3375
Total: 22 247
Tiling works
1 Wall cladding with tiles (size 250-250 mm) bath, toilet sq.m 25 850 21250
2 Installation of the hatch PC. 1 418 418
3 Tile hatch device (with installation of the mechanism) PC 1 1100 1100
4 Laying tiles on the floor (size 300-300 mm) bath, toilet, balcony sq.m 10 700 7000
5 Drilling holes in tiles PC. 12 160 1920
6 Grouting ceramic tiles(monocolor) sq.m 35 100 3500
7 Facing of thresholds from tiles r.m 1 1000 1000
Total: 36 188
Floor arrangement
1 Waterproofing floors in bathrooms sq.m 4,4 185 814
2 Leveling screed device up to 3 mm sq.m 54,4 150 8160
3 Laying laminate (with backing) sq.m 54,4 280 15232
4 Installing the nut r.m 3 150 450
5 Installation of skirting boards r.m 65 130 8450
Total: 33 106
Ventilation work
1 Ventilation box insert PC. 1 319 319
2 Installation of a ventilation duct (up to 2 m) PC 2 1650 3300
3 Fan installation (with connection) PC. 2 308 616
Total: 4 235
Heating
1 Alteration of the heating radiator inlet assembly PC. 3 4500 13500
2 Heating radiator installation PC. 3 1500 4500
3 Removal / installation of a radiator for finishing work (without dismantling the bracket to a ready-made place) PC. 3 500 1500
Total: 19 500
Plumbing work
1 Temporary water supply device set 1 1650 1650
2 Plumbing device r.m 6 600 3600
3 Plumbing fixing r.m 6 120 720
4 Installation of a fine filter with pressure regulator PC. 2 1400 2800
5 Collector installation (complex of works) PC. 2 2000 4000
6 Laying of pipes HGV (m / layer, p / propylene, p / ethylene) r.m 26 270 7020
7 pad sewer pipes(PVC) r.m 5 330 1650
8 Thermal insulation of pipes r.m 26 50 1300
9 Installation storage water heater(boiler) PC. 1 3300 3300
10 Installation of a toilet bowl "Compact" PC. 1 2805 2805
11 Installation of "moidodyr" PC. 1 3000 3000
12 Mixer installation PC. 1 850 850
13 Installing a hygienic shower PC. 1 850 850
14 Installing a heated towel rail PC. 1 3300 3300
15 Bath installation PC. 1 3700 3700
16 Installing a bath mixer on a rod PC. 1 1250 1250
Total: 41 795
Electric installation work
1 Shtraba device up to 30x30 mm r.m 16 275 4400
2 Sealing the shtrab r.m 16 35 560
3 Cabling r.m 255 50 12750
4 Installing the socket (with socket device) PC. 33 300 9900
5 Installation of electrical distribution board of the consignment note PC. 2 650 1300
6 Installation of automatic protection devices, diff.automatic devices, RCDs PC. 12 250 3000
7 Installation of a socket, switch PC. 30 130 3900
8 Installation of TV, Telephone, Internet sockets PC. 3 180 540
9 Installation of TV, Telephone, Internet splitter PC. 1 280 280
10 Installation of a built-in (spot) lamp PC. 6 200 1200
11 Electric underfloor heating installation sq.m 2 750 1500
12 Installation of underfloor heating relay PC. 1 350 350
13 Marking of electrical installation sites (without project) PC. 33 35 1155
Total: 40 835
Total for work: 360 932
Total according to estimate No. 4: 360 932

Table No. 1 of the consumption of rough material.

Table No. 1 on the consumption of construction and finishing rough material in an apartment with a total area of ​​64 m2 a new building at the address: RC "Finsky-Potapovo 3A" microdistrict.

Examples of samples of a table of accounting for the consumption of rough material

Name

material

pcs / m2

bags

price

general

price

1 "Rodband" mixture with a layer thickness of no more than 2 cm 87 370 32190
2 Sand concrete M300 with a screed layer thickness of no more than 5 cm 145 160 23200
3 Plaster lighthouse 0.6 45 40 1800
4 Plaster lighthouse 1.0 12 45 540
5 Betokontakt "EURO" 3 1350 4050
6 Primer "Prospectors" 5 450 2250
7 Foam block No. 5 in pieces 6 45 270
8 Foam block No. 7 in pieces 84 55 4620
9 Waterproof gypsum plasterboard 12 2 370 740
10 Plaster putty "Fugenfuehler" 1 750 750
11 Mounting glue for Perlfix blocks 3 320 960
12 Tile adhesive "Flizen" 6 350 2100
13 Self-leveling floor "Prospectors" 8 320 2560
14 Putty "Vetonit" LR + 9 750 6750
15 Spider web "Oscar" 50m2 1 1150 1150
16 Profile 27/28 "Knauf" 6 100 600
17 Profile 60/27 "Knauf" 4 130 520
18 Finishing putty "Pro Form" 1 1350 1350
19 Suspension "Knauf" 40 20 800
20 Film density -150 60 50 3000
21 Beams 50/50 planed 3 200 600
22 Planed board 150/20 3 300 900
23 Trash bags 120 10 1200
24 Oscar spider web glue 1 1350 1350
25 Waterproofing coating "Ceresit 65" 6 750 4500
26 Rule 2.5 1 500 500
27 Rule 2.0 1 400 400
28 Rule 1.5 1 300 300
29 Dowel nail 60/40 2 250 500
30 Facade mesh 160 density 1 1250 1250
31 Putty "Uniflot-Knauf" 1 1100 1100
32 12 liter bucket 2 120 240
33 Bucket 20 liters 2 180 360
34 Basin 60 liters 1 350 350
35 Masking tape, paper 5 70 350
36 Packaging tape 2 70 140
37 Self-tapping screws 0.35 universal 2 130 260
38 Self-tapping screws 0.65 for wood 1 130 130
39 Self-tapping screws 0.75 for wood 1 130 130
40 Self-tapping screws 0.25 universal 2 130 260
41 Galvanized painting corner 18 35 630
42 Alabaster in bags 1 280 280
43 Silicone in a tube 1 140 140
44 Glue in a tube "FixAll" 1 420 420
45 Crosses 1.5 for tile joints 4 100 400
46 Tile Joint Wedges 2 100 200
47 Cable NUM 3 / 1.5 "Sevkabel" 100 35 3500
48 Cable NUM 3 / 2.5 "Sevkabel" 150 47 7050
49 Cable NUM 3/4 "Sevkabel" 36 82 2952
50 Cable NUM 3/6 "Sevkabel" 5 95 475
51 Corrugation 16 100 3 300
52 Corrugation 20 200 4 800
53 Internet cable "FTP" 10 22 220
54 TV cable "SAT 703" 40 25 1000
55 Telephone cable "KSPV" 10 12 120
56 Crab TV 1/3 1 250 250
57 Insulating tape 1 40 40
58 Punched tape 1 180 180
59 Lamp 150v 5 40 200
60 Socket boxes for concrete 50 10 500
61 Automatic machine 10 amp. "ABB" 2 150 300
62 Automatic machine 16 amp. "ABB" 3 150 450
63 Automatic machine 25 amp. "ABB" 5 150 750
64 RCD "ABB" 1 1250 1250
65 DIF automatic machine 25 amp. 1 1350 1350
66 Rebar 12 3 220 660
67
68 Lifting material "in tons" 8 1500 12000
69 Delivery of materials "gazelle" 4 1500 6000
70 Total: 147 787

We will send the material to you by e-mail

Long-awaited renovation in the apartment! In order for you not to hate it in a couple of years, you need to prepare for it. An example of an estimate for the renovation of a premise will help with this, because such data will show how much and in what volumes you need to invest to get your dream home. This is not just a list of purchases, but a whole document that can be entrusted to draw up also to specialists, but here be prepared to overstate costs. You can just as successfully compose it yourself, it is only important to know how.

The estimate includes all expenses, calculates any unforeseen costs, including the services of specialists in different directions. In order to make an estimate, you need:

  • Measure the premises. This includes the height and length of all walls, the length of the wiring, cables, water and heat communications, if any, will be included in the repair. After receiving information on the dimensions, you can, which will become the basis for calculating the necessary rough and finishing materials. It is important to have data on the area of ​​the walls, floor and ceiling.
  • Based on the data obtained, it is necessary to calculate the rough materials - make a margin of at least 5-10% at the same time.
  • Next comes the selection and calculation of the necessary decorative materials.
  • Now for the most interesting and exciting thing: price monitoring. You need to know how much the rough and Decoration Materials, the cost of the services of a designer and a team of repairmen, plumber, electrician and other specialists who may be involved in the repair process. It is best to draw a table and indicate several options for each item - this will allow you not to make a mistake with the choice.


All the data obtained must be recorded, and then drawn up in one table: so you will have a work plan + the cost of materials and the cost of paying for the work of specialists. It is also necessary to indicate the timing of the work, and if the infusion of funds is partial, then their dates of such receipts.

Nuances

The estimate is not only technical information, it includes an element of creativity. The technical aspect is at least minimal knowledge of the processes that will occur during the repair, understanding of the market building materials, what is needed for what.


A creative approach is a competent distribution of all cost items in accordance with the needs at a particular stage of work. It is important to take a balanced approach to the selection of the team, if you will trust the specialists. Do not flatter yourself on low prices- it is likely that the quality will be the same there. Better make an estimate yourself, the minimum data and numerous templates will help you with this. Why is it better to do it yourself? Everything is very simple: when ordering an estimate from a construction company, you will surely receive as a result 20, or even 30% more amount than it actually is. If you have doubts about the truth of the data, then you can easily use the services of one more "specialist" - these are auditors. As practice shows, the cost of the estimate will decrease by at least 10%.

Examples of

The photo below is an example of an estimate for the renovation of a kitchen room. All types of work are categorized for convenience. Such options for estimates for repairing the premises will help you navigate and quickly find out how much money will go to individual parts.

Dismantling works are carried out in separate subsections. When conducting overhaul there will be a need to dismantle not only or old finishes, but also pipes, including sewer ones. And given that the plumbing is connected in the apartment, this work will also affect the bathroom. It is rational to carry out repairs in the bathroom / toilet and kitchen together: this way you can save money. This is followed by the treatment of walls, floors and ceilings. Here you can see that the roughing and finishing works are included in one table, we would recommend separating them.

Plumbing installation is also an important step in budgeting. If it is better to add the riser to specialists, since you have decided to use their work, then it is quite possible to connect the mixer yourself, no serious skills or complex tools are needed for this.


As you can see, there are columns with units of measurement, areas and lengths of all work points. For ease of calculation, the price per unit of work is indicated and then the total cost. The estimate will pull more funds if you entrust the construction company with the purchase of materials. But be careful here: it is often practiced to replace high-quality materials and components with low-grade ones. Therefore, it is important to control every stage of the work.

The following is an approximate estimate for the repair of the entire apartment, here is a slightly different drawing up scheme, but the meaning is the same. That is, the unit prices and the total cost of the work are indicated. As you can see, here the customer, most likely, will entrust the company with the purchase of materials, for this there is a special column, although it is possible to purchase it himself, and enter this data for clarity. Here is a more thorough study. Pay attention to the last point: the customer even took into account the cost of running construction waste, which is also important when carrying out a major overhaul.

An example of an estimate for an apartment renovation